Client Case Studies
–
Three-storey Residential Lofts – Marryatville, SA
PROJECT SUPERVISION AND ADVISORY

Construction is progressing well on our Kensington Road project in Marryatville, where we’re delivering three‑storey residential lofts above two existing retail tenancies.
This development makes smart use of previously underutilised space behind the shops, adding high‑quality residential capacity without disrupting the established character of the streetscape. A key part of our approach has been ensuring the new structures remain visually discreet from the main road, preserving the look and feel of the existing commercial frontage.
Stormwater Flood Management – Kensington Gardens, SA
PROJECT MANAGEMENT & CONSTRUCTION SUPERVISION

Flooding occurred in front of two garages at a residential unit complex in Kensington Gardens. Epic Projects was engaged to provide expert stormwater management advice to prevent future flooding. We completed the design plans and technical specifications, and also provided tendering, contract administration, project management, and construction supervision services to ensure the solution was delivered effectively.
The property had two separate stormwater drainage systems, one located at the front of the site, and another at the rear, near the garages that were affected by the flooding. The front drainage system collected runoff from the shared driveway and surrounding paved areas near the front units. The rear system, where the flooding occurred, included a 300 x 300 mm grated drain designed to capture runoff from the rear section of the property. This rear drain was connected to a pump chamber containing a submersible pump. The pump transferred water through a rising main, which discharged into the same grated drain at the rear. From there, a 100 mm PVC pipe carried the water to the roadside gutter.
All roof downpipes from the surrounding residences were connected to a separate underground drainage system. Based on site observations, no connections from the roof drainage system were found to be linked to the driveway drainage system. It was concluded that stormwater from the roofs did not contribute to the flooding issue.
To resolve the problem, the existing pump was retained and improved the system by installing a new underground stormwater storage tank beneath the common driveway. The tank had a capacity of at least 5000 litres. A new pump was also installed, capable of delivering flows of at least 1.8 litres per second through the existing rising main. Additionally, the original drain grate was enlarged to 450 x 450 mm to reduce the risk of blockages.
These upgrades successfully eliminated the minor flooding in front of the garages. The works also provided 100 mm of freeboard (protection) above the garage floor levels during a 1-in-100-year average recurrence interval storm event. Overflow along the eastern side of the affected unit was also prevented for events of this magnitude.
Dougstock Music Festival Stage – Willunga, SA
ENGINEERING REVIEW

Carpark Upgrade for Funeral Home – Elizabeth North, SA
STORMWATER DRAINAGE

Fuel Station Development – Yunta, SA
STRUCTURAL AND ARCHITECTURAL DESIGN

Nando’s Restaurant – West Lakes, SA
RESTAURANT FITOUT

– All new internal and external signage and a bulkhead
– A suspended partition wall (9m long × 3m high) opening to a raised ceiling of 6m
– Suspended shelving and Nando’s signature pendant lightingThe existing structure was complex, featuring a 6m high ceiling, long open spans and suspended internal clad walls. New structural beams spanning over 10.4m were designed to ensure both structural integrity and minimal deflection. With no supporting slab below, all suspended shelves and architectural features had to be carefully designed and attached to existing beams to ensure load safety, stability and visual cohesion.
Jarvis Cars Renovation – Norwood, SA
STRUCTURAL UPGRADES AND CIVIL DRAINAGE


Fire Damaged Home – Adelaide, SA
STRUCTURAL ASSESSMENT

Wildman Farm – Korunye, SA
ENGINEERING AND STRUCTURAL DESIGN

The new addition offers flexible event space that expands the venue’s capacity while keeping its cosy and rustic charm perfect for capturing beautiful photos and celebrating with loved ones.
New Adidas Store – Burnside, SA
SHOP FITOUT

One of the most anticipated additions to Burnside Village is the brand-new Adidas store, which officially opened its doors on 9 October 2025.
Epic Projects and Consulting brought the vision to life, delivering the structural design for this stunning fit-out. A true standout, the store features a striking curved bulkhead and glazing structure, creating a sleek, modern look that perfectly complements Burnside Village’s vibrant new atmosphere.
Three-storey Residential Lofts – Marryatville, SA
PROJECT SUPERVISION AND ADVISORY

New Contract Won – Ingle Farm, SA
CONTRACT MANAGER AND SUPERINTENDENT

The Walkleys Road Corridor is well situated around residential housing, as well as being close to public transport, schools, places of worship, and a large shopping centre. The development will not only integrate seamlessly with its surroundings but will also introduce enhanced footpath and road networks to improve local connectivity, along with new high quality amenity areas that will serve new and existing residents.
P&R Electrical Mezzanine – Brighton, SA
MEZZANINE CONSTRUCTION

Our latest project involves the construction of a new mezzanine floor within the Brighton store, designed to increase storage capacity and improve operational efficiency. It’s a smart use of vertical space that supports their growing stock needs while preserving valuable ground-floor workspace.
Truck Fuelling Facility – Peterborough, SA
STRUCTURAL & CIVIL ENGINEERING

Epic Projects provided structural and civil engineering, and architectural design services for a fuel facility in Peterborough, featuring two fuelling stations with an overhead canopy measuring approximately 6m x 17m. Our work includes site drainage, stormwater management, and overall site planning. Additionally, we managed the project through the planning approval process, collaborating closely with the Peterborough Council, the Environmental Protection Authority, and the Department of Infrastructure and Transport. The project received successful approval and was constructed on time and to budget given the constraints of Regional work.
Architectural Design and Structural Engineering of Beds for Boarding School – Adelaide, SA
ARCHITECTURAL DESIGN & STRUCTURAL ENGINEERING

Epic Projects and Consulting recently completed a comprehensive architectural design and engineering check for a series of single and bunk beds for a boarding school in Adelaide. The project required strict adherence to Australian Standard AS4220:2010, which outlines the design and safety requirements for children’s furniture. We focused on ensuring that the joinery was structurally sound, with particular attention paid to the load-bearing requirements, including forces acting on the stair treads, guard rails and overall bed framework. The design was carefully engineered to provide both safety and durability, ensuring that the beds could withstand daily use and pressure from the students using them. The final design not only met all regulatory requirements but also provided a robust and safe solution that could withstand the rigorous demands of a busy school environment.
Structural Assessment of Fire Damaged Shed – Hart, SA
STRUCTURAL ASSESSMENT & RESTORATION

We conducted a comprehensive structural assessment of a farm shed in Hart, South Australia, which had sustained significant damage due to a hay fire. The fire was the result of spontaneous combustion from hay bales that had been stored inside the shed. Our primary objective was to determine whether the structure could be feasibly repaired or if it would require complete demolition and reconstruction. The assessment focused on identifying all affected structural components and evaluating the severity of the damage to determine which parts could be salvaged and which would need replacement.
Following a detailed on-site inspection and evaluation, we concluded that the shed could be successfully repaired, avoiding the need for a full rebuild. The repair work involved replacing the entire roof, including all iron sheeting, flashings and purlins. In addition, we replaced all damaged wall sheeting to restore the shed’s weatherproofing and appearance. Structurally, two roof trusses and one column were found to be beyond repair and were fully replaced.
To further enhance the shed’s durability and prolong its service life, all remaining columns were blasted and repainted. These measures ensured that the structural integrity of the shed was not only restored but also improved.
Burton Community Hub – City of Salisbury
CONTRACT AND PROJECT MANAGEMENT

The Burton Community Hub replaced the Community Centre and Salisbury West Library to provide a new exciting space perfect for study, community programs and meetings. The design and construction of this project took a total of 6 months to complete with a budget of $6.25 million. It was important that the local community was also consulted for the design, so the City of Salisbury sent out surveys to the residents to ask for their input. A total of 239 people responded to the survey. The project included the construction of ‘The Shed’, which is a community shed facility filled with lots of carpentry and other tools for people to undertake personal and community projects. The Shed was also designed to welcome individuals with disabilities to participate and engage in activities and encourage skill building. The ‘Community Garden’ was also implemented with the intention of promoting healthy living by allowing local residents to come together and grow fruits and vegetables. The goal of this garden was to educate the community on sustainable gardening practices, connect with other residents and share the food that they grow.
Operations Centre Upgrade – City of Salisbury
CONTRACT AND PROJECT MANAGEMENT

The operations centre located in Salisbury South required an upgrade to allow for a more efficient layout, improvements in traffic management and safety, the wellbeing of staff and a more flexible working environment, matching new mobile technology. We were recently engaged to oversee project management of the upgrade. The design and construction took one year to complete with a budget of $4.4 million. The project focused on the following objectives:
- Building design to improve the way teams interacted and provided opportunities for better collaboration through better planning and layout.
- Improved work and traffic flows to maximise space and movement, aiming for efficiency, effectiveness and productivity.
- Addressed current storage issues and reorganised and unified the storage. Explored and implemented ideas to reduce/manage onsite storage and consolidate assets and tools.
- Designed workspaces and amenities to have a warm and friendly ambiance. Wet area upgrades improved amenities (toilets, lunchroom and kitchen). Provided meeting rooms, training spaces and breakout areas, including a Café Style touchdown area.
- Designed safe, compliant and environmentally responsible workspaces.
Kangaroo Island School Campus – Stormwater Management
STORMWATER MANAGEMENT

Epic Projects and Consulting became involved in this project with the aim of providing a comprehensive civil engineering solution to address flooding issues that had arisen due to the gradual and uncoordinated development of the site over the years. The ongoing piecemeal development had led to a significant increase in impervious surfaces, which, in turn, contributed to an increase in stormwater runoff. This runoff was particularly problematic, not only from the newly developed areas but also from the neighbouring Council land situated above the site.
To fully understand the scope of the issue, we first conducted a detailed site survey, which included a thorough site inspection to assess existing conditions, topography and the flow of water across the area. This allowed us to identify key problem areas where water pooling and runoff were most likely to occur, as well as areas where drainage systems were insufficient or inadequate.
Based on these findings, we devised a series of tailored civil solutions that would mitigate the risk of stormwater flooding. Our strategy included redesigning drainage systems to better capture and direct runoff away from vulnerable areas, enhancing the permeability of certain surfaces and implementing water retention measures. This approach not only alleviated the immediate flooding concerns but also aimed to improve the overall stormwater management system for the long-term resilience of the site.
The final design ensures that stormwater is managed more efficiently, reducing the risk of flooding during heavy rainfall events. By carefully balancing environmental considerations with engineering best practices, we have helped to create a more sustainable and resilient site that is better equipped to handle future stormwater challenges.
Rear Boundary Fence and Stormwater Management – Athelstone, SA
Stormwater Management for Residential

Stormwater has always been a tragic issue. At Epic Projects, we have been involved in numerous stormwater management projects. One of our current projects is to manage stormwater runoff that was claimed to cause problems in the neighbour’s garage, and also damaged the rear boundary fence between the two properties.
The challenge we faced in this project was to prove that the runoff water from our client’s house did not damage the fence and to the neighbour’s garage, and thus provide solution to minimise the problems.
There is a gradient fall in the garden toward the rear. However, we believed this did not contribute to damage the neighbour’s garage simply because most water flow underground and the garage would have been cut into the face of the sloping land. The sloping land continues into the neighbouring house and has lawn that drains to rear of the house contributing to its own stormwater. The neighbour is contributing to its own stormwater issues if that water is not being collected at the rear of the house.
To solve minimise the amount of runoff water, we had performed a stormwater calculation to determine appropriate numbers and sizes of soakage pits. The final solution was to install three soakage pits to drain runoff water from 6×4 meters shed and small veranda (26-meter squares).
To solve the issue relating to the slope from the rear yard to north-west, we proposed a 3x2x0.5 soakage pit.
Temporary Fence Testing
Premier Fencing

Epic Project was involved in reviewing and presenting certification for temporary fence testing, followed the Australian Standard AS 4687-2022. Temporary fence testing is important to ensure that the fence is safety to install, providing protection to the public and the workers on site.
To check conformance to the AS 4687-2022, the code allows a combination of design analysis and physical testing. There are four different types of testing required by the code, which are: Impact test, Foothold aperture test, Simulated climbing test and Simulated wind test.
Epic Projects assisted with physical testing for the Impact test and the Foothold Aperture Test. The set-up for both tests were followed by Section 4 and Section 5 of Australian Standard AS 4687:2022 and Appendix B and Appendix C AS 4687.2:2022.
Simulated climbing test and simulated wind test were both designed and analysed in accordance with the requirement of Australian Standard AS 4687.1:2022 Clause 5.1, whereas in simulated wind test, AS 1170.0:2022 was used accordingly to AS 4687.1:2022 to determine the wind loads.
Film Set Design – Glenside Studio, SA

In response to major changes in Australia’s waste management strategy, East Waste required expansion of its operation facilities. The CEO approaches us directly to find a solution to expanding their operation centre, and providing new amenities, disability access throughout the whole building including external access. The challenge for this particular project was the consultation with the lease holder, senior management all the way down to the operators and truck drivers. An additional challenge was to undertake works safely while the facility operated. The challenges were overcome by good planning and management, and spending focused time on listening to all the stakeholders, balancing the requirements. We have provided the planning architectural, engineering design and tender for this project. Now we are taking on the construction contract and project management.
100 Homes Program – SA Wide
CONTRACT AND PROJECT MANAGEMENT OF 100 HOMES ACROSS 17 SITES AND 9 CONTRACTORS
An affordable housing initiative by the SA Government, the 100 Homes Program expanded 17 sites across SA. The complexities that emerge from a project of this size showcase Epic Project’s ability to manage the extensive workload, and still deliver the project on time and on budget. As project and contract management, Epic Projects conducted site visits to each lot every two weeks. We maintained seamless internal quality systems, training of staff and utilised web-based reporting tools to overcome the inevitable challenges that accompany such a broad project. We were able to keep on top of the consistent project variations, extension of time requests and progress certifications with diligence to maintain timeframes and cost management.
Hobson Engineering Warehouse – Direk
CLIENT-SIDE SUPERINTENDENT, PROJECT MANAGEMENT, DESIGN REVIEW

This 8000m2 warehouse was a design and construct project, challenging due to the extensive area and tight time frame. Not having the design produced independently but through the contractor created its own complexities and challenges in ensuring that the contractor delivered on the requirements outlined in the design brief, and offered value for money. This is very different to the traditional design first with detail and specific specifications and tendering on the design. There is less control of the design process and outcomes. The contract also provided many items that were provisional sums that left the principal exposed to potential variations and lack of clarity of scope. To overcome this, refined communication during site meetings and resolving unknowns as soon as possible enabled the provisional sums to be priced. Another key challenge was having a very flat slab with very tight tolerances. This was required due to the robotic machinery which would travel over the surface. To overcome this challenge, specialist concrete contractors were carefully managed to ensure the flatness was achieved and no cracking of the concrete slab.
SRWRA – Seaford Heights
CONSTRUCTION SUPERINTENDENT


Southern Region Waste Resource Authority (SRWRA) is a joint subsidiary established by the Cities of Onkaparinga, Marion and Holdfast Bay. The authority provides waste management services and are one of the major landfill operators in South Australia. SRWRA have been implementing a gas management plant, in which methane gas is extracted from the 100,000 tonnes of landfill they receive annually. Through this innovative and conscious effort, they have achieved the CO2 abatement equivalent to taking 26,000 cars off the road[1]. At Epic Projects & Consulting, we are driven by innovation and were therefore excited to work with SRWRA, providing project management for a shed extension. This project is just a small insight into the $21million material recycling facility that is set to provide work and boost economic growth for the Southern region.
Plans for the new material recycling facility began as a response to China’s ban on contaminated recycling imports, which in turn hiked up costs as waste products had to be transported to other facilities. The new facility, located in Seaford Heights, will allow for price control, as well as a host of other benefits. According to Mark Booth, SRWRA Chairman, the new project will not only improve recycling in the southern region, but also provide 37 full time equivalent jobs, stimulate economic growth and attract circular economy industries. According to the Waste Management Review, funding for the project includes $5million towards the construction of the plant, and a further $5million for an economic development fund to support the co-location of compatible industries.[2] The shed extension project, managed by Epic Projects & consulting is just the beginning of the exciting new facility.
[1] https://srwra.com.au
[2] https://wastemanagementreview.com.au/tag/srwra/
Cellar Construction – Rose Park


We provided the design of the structural concrete and specification of the concrete strength that was applied during construction and the cellar was made to be 2.8m deep with a 180cm thick concrete wall. This Cellar was constructed using the ‘shotcrete’ method. This means the concrete was sprayed through a hose and pneumatically projected at a high velocity onto the desired location.
In this instance it was applied over the steel bars that were used as reinforcement, in some cases, mesh or fibers can be used as an alternative. Shotcrete is an in-situ method, meaning it occurs on site. Through this method the concrete is placed and compacted simultaneously due to the force of the nozzle and is able to be sprayed onto any type of shape or surface. After the shotcrete was finished being utilised the floor was then constructed over the top using bondek slab.
Lola’s Pergola
PLANNING, DESIGN AND CONSTRUCTION SUPERVISION

Epic Projects and Consulting provided the engineering and construction advice for Lola’s Pergola – a temporary marquee structure designed as an outdoor bar located on the Torrens Riverbank for the 2014 Adelaide Festival.
The challenge Epic Projects faced was to design a structure that was suitable for large volumes of people to gather and celebrate that didn’t compromise and restrict the space. Featuring an array of talented Australian and international DJs, the structured provided the space and atmosphere for the festival.
Inglewood Residential Bridge

One of our recent projects was designing a small residential bridge across a creek. We worked closely with our clients to resolve all the potential issues that other companies they had spoken to had said were unsolvable. We even offered suggestions on materials that would complement the landscape and found ways for them to save money on design costs during the planning process. Needless to say, the clients were thrilled with our work and even left us this testimonial and comment on Google;
“Joe is a great bloke and helped my wife and I build a 9 metre span bridge on our property. He definitely focuses on customer service and did a great job keeping the council in line we really couldn’t have asked for a better engineer on the job! Thanks again Joe and team.” – Bobby P.
